Return to Website

MoldMaker's Forum

This is a place where those involved with the moldmaking industry can come together to share information, ask questions, offer tips, etc.
(It may be necessary to refresh/reload your browser window after posting in order to see your post as well as any other new posts.)

***Posts containing negative opinions about specific products or services will be deleted if no contact information is provided.***

If you have problems using this forum, or need technical advice, please send an email to info@ctipublishing.com.

*The views and opinions expressed in this forum are not necessarily the views of MoldMaking Technology magazine.*

MoldMaker's Forum
Start a New Topic 
Author
Comment
Mold Manufacturing Managemnt

Mould Manufacturing mangement consultancy



We are located in Pakistan having following facilities

1-
-CNC Milling
-CNC Lathe
-EDM conventional with orbicut
-Some supporting machine like surface and cylinderical grinders, furnances, conventional lathes and milling etc.etc.

2-
Human Resource
4 Associate Engineer Dies and Molds
10 Machinist un educated but experienced
3-
CAD Section
1-Two designers

4-
Activity Planning & Control (APC) Section
One person schedule and reschedule the whole of acitvities and assign to the shop floor and record the feed back on daily basis.

5-
Organization hirarchy

Cheif Designer
- Supervises the design Section
- Supervises the Manager Tool Room
- Responsible to deliver drawings based on properly evaluated desgn.
- Directly involved in R&D.


Mnager Tool Room
- Report to Cheif Designer
- Supervise the Planning & Controlling Section.
-Supervise the Machinning & Assembly Section.
-Actively participate to Designing Committee.
-Responsible to deliver according to drawing received from Desining section.

Process
Detailed drawings based on evaluated drawings are handed over to Manager Tool Room who firstly get the assigned job planned by elocating resources and than send this to Machining section. Once the whole machining is completed according to drawing the assigment is handed over to mold assembly area. Where Mould is assembled , make this ready for trial.


The Problems
-Most of the time mold are not delivered in time
-Most of the time mold trials escelate more than 5 or 6 trial where as our standard is 3 trials.
-Most of the time delivery time is slipped.

Queation

Keeping in view the above situation , Can somebody suggest to improve to our dark areas.

Tariq